Building Modernization Project

Overview

Modernization efforts on the River Ridge campus began in July 2022. At the end of this five-year project, we will enjoy a beautiful facility that meets the needs of our students and community now and into the future. We will have upgraded athletics facilities, classroom spaces, and a more cohesive and connected campus.

A major project such as this will come with disruption, just as construction at Timberline and North Thurston high schools did. The goals of the RRHS staff and the construction team are to:

  1. Minimize disruption to the learning environment throughout this project.
  2. Ensure student and staff safety.
  3. Keep staff and families informed as work progresses.
  4. Ensure athletic teams and other activities have adequate alternative spaces

Thank you for your partnership as we navigate this major project. Together we are building our future!

Project Details

River Ridge High School modernization

Major modernization work began in July 2022 at River Ridge High School. The project includes improving classroom space and performing arts facilities, connecting the main building to the auxiliary gym, and converting the football field to artificial turf with lights. Scheduled completion: 2027.

Phase 1 (Summer 2022-Fall 2023)

  • New Hoh Street access road started
  • Reroute and installation of new utilities (sewer, power, gas, stormwater)
  • Portable classrooms placed on site (17 buildings, 34 classrooms)
  • New tennis court constructed in new location
  • New athletic locker rooms and weight rooms constructed
  • Pool mechanical and electrical replaced
  • New Phase 1 bus loop created
  • Temporary parking installed
  • Main and auxiliary gym improvements made

Phase 2 (Fall 2023-Fall 2025)

  • Demolition of Admin Building, House A, and athletic/weight room building
  • New administration, kitchen, and classroom addition constructed
  • Renovation of existing bus loop and front parking lot
  • Commons area reconstructed
  • Construction of temporary kitchen

Phase 3 (Fall 2025-Summer 2027)

  • Music spaces constructed
  • Theater and CTE building renovated
  • Demolition of Houses B, C, and D
  • Football and athletic fields constructed
  • New student parking and Hoh Street connection completed