Latest Construction Updates
Modernization work continues on time and on budget! The River Ridge campus will be closed over summer 2025 to ensure safe and efficient construction efforts. The work this summer will include:
- Completing construction of the new classroom wing and library to open fall 2025!
- Continuing construction of the administration and the band and choir/orchestra wings.
- Beginning construction of a spin room for physical education.
- Renovating the north portion of the Career and Technical Education building.
- Removing the portables.
- Re-roofing the swimming pool building.
- Refinishing the main gym floor.
- Beginning the retaining wall for the new football field.
- Regrading and paving the north bus loop.
- Constructing the new southwest student parking lot.
- Repaving the intersection at the Hoh Street bus loop entry.